Life Reimagined

Construction Updates

June 18, 2020

Framing Inspections

Building 5
Final Framing inspection is expected this week!
Building 8
Final Framing Inspection six weeks from now – End of July!
Building 9
Final Framing Inspection is estimated to be sometime in August. Most of the first floor is framed!

June 11, 2020

June 11th Update

  • Building 9: Final Framing Inspection is estimated to be sometime in August - Most of the first floor is framed
  • Building 8: Final Framing Inspection six weeks from now – End of July
  • Building 5: Final Framing inspection is expected this week!
June 11June 11

June 4, 2020

June 4th Update

  • Building 9: The slab has been poured. Framing will start the following week!
  • Building 8: Ground floor patios have been poured. Rough plumbing is underway.
  • Building 5: Estimate from the Builder is Final Faming Inspection the week of June 15-19. Electrical is mostly done and drywall backing is being installed for fireplace installation.

June 2, 2020

Colorado Craft Brokers Has Joined Our Team!

You may see new faces on site! Colorado Craft Brokers will be closing out the remainder of River West’s sales. CCB is owned by brokers Kim and Leslie Hebron. They have been serving residential and commercial clients for more than 4 decades. Matthew Strempke has joined the CCB team and will be co-listing remaining units alongside Kelly Hepburn. Stop by the sales trailer to say hello or to book an appointment!